The plan

Phased so the building is protected — and open — sooner.

The City's 2023 study put whole-complex code work at up to $20 million. We don't spend it all at once.

Four phases

Each phase opens only what is approved and funded.

Milestones for stabilization, financing and occupancy come with City step-in and reversion rights — so the public interest is protected at every step.

  1. Phase 01

    Investigate & design

    Professional surveys, code analysis, cost estimate and financing — before any commitment is made.

  2. Phase 02

    Stabilize the Castle

    Roof, water entry, masonry and security — protecting historic fabric while full restoration is planned.

  3. Phase 03

    Open the annex

    First occupancy of the 1964 annex after approved construction, inspections and occupancy permits.

  4. Phase 04

    Restore & grow

    Full restoration of the Castle and 1924 addition, opening heritage rooms and the auditorium to the city.

Key dates

The road to December 15.

Nov 15Join the core RFP team
Nov 19Written questions to the City due
Dec 15Proposals due, 2:00 p.m.
Early 2027City's initial review